Alexis Nakota Sioux Nation

Alexis Nakota Sioux Nation

Mini (water) System Project Wild Phase 2

Project background

Alexis Nakota Sioux Nation had an existing treatment process that was unable to produce water capable of meeting Canadian Drinking Water Quality Guidelines. BCL was retained to complete the planning, design and construction engineering of a new water system for the community. After completion of a feasibility study, the most advantageous option involved connecting to the treated water supply main from the West Inter Lake District (WILD SUPPLY), which was delivered to the Nation’s boundary.

Project highlights

  • 261 square metres building on a 1,160 metres cubed reservoir.

  • 175kW natural gas generator to supply emergency backup power.

  • Distribution and standby pumps controlled by variable frequency drives.

  • 8,300 m total of water distribution and service.

  • 256 square metres maintenance building.

Services Provided

  • Preliminary Design

  • Detailed Design

  • Tendering

  • Construction and Resident Engineering Services

  • Contract Administration

Consultant

Project Manager

Contractor